Weekly Construction Update 2/17/2023

TRAFFIC IMPACT AND DURATION:

Crews will be onsite Monday through Friday between the hours of 7:00 a.m. and 5:00 p.m. Traffic impacts will be restricted to the hours of 9:00 a.m. and 4:00 p.m. Monday through Friday.

Crews will continue working behind the bridge piers on both sides of the interstate bridges over U.S. Routes 2/7 (U.S. 2/7) under lane closures and lane width reductions.

This work will require closures of the outermost lanes on U.S. 2/7 in both directions. In addition, lane width reductions along the I-89 southbound onramp on the east side of U.S. 2/7 and the I-89 southbound offramp on the west side of U.S. 2/7 will be in effect. The I-89 ramps will remain open.

CONSTRUCTION ACTIVITIES:

Along the east side of U.S. 2/7, crews will continue installing the retaining wall behind the bridge pier. This work will be completed under lane closure of the outer northbound travel lane on U.S. 2/7 and lane width reduction of the I-89 southbound onramp. 

Along the west side of U.S. 2/7, crews will continue removing material including ledge over the next several weeks to facilitate the installation of the retaining wall. This work will include hammering to break up the ledge for removal. This work will be completed under lane closure of the outer southbound travel lane on U.S. 2/7 and lane width reduction of the I-89 southbound offramp.

Work continues on the installation of the retaining wall along the east side of U.S. 2/7.

Crews removing materials including ledge to facilitate the installation of the retaining wall along the west side of U.S. 2/7.

LOCATION: U.S. Routes 2/7 (U.S. 2/7) in Colchester from the Winooski town line and continuing north for 1.05 miles to Sunderland Woods Road.

PROJECTED COMPLETION: Contract 1 Spring 2024, Contract 2 Summer 2026